This chart was submitted in prepared testimony that Michael Amarosa, vice-president of TruePosition, gave to the U.S. Senate Sub-Committee on Commerce, Science and Transportation. The chart compares the milestones (or deadlines) set by the FCC originally, and the waivers the Commission granted to the five major carriers in mid-October 2001. Download an Acrobat (pdf) version of the chart as it was originally submitted to the Sub-Committee. Note: To make the milestone differences obvious, we've color-coded the chart to indicate: green = milestone is the same as the FCC's original rule, red = milestone is 1 year or more after the FCC's original rule. updated 8/18/05

FCC Rules

Verizon

Sprint

AT&T

Cingular

Nextel
Begin selling ALI-capable handsets by Oct. 1, 2001 Begin selling ALI- capable handsets by Dec. 31, 2001 (three months after rule) Begin selling ALI- capable handsets by Oct. 1, 2001 (same as rule) AT&T must follow the handset deployment schedule, but has reduced accuracy requirements for 2 years Begin selling ALI- capable handsets by Oct. 1, 2001 (same as rule) Begin selling ALI- capable handsets by Oct. 1, 2001 (same as rule)
25% of all new handsets must be ALI- capable by Dec. 31, 2001 25% of all new handsets must be ALI- capable by July 31, 2002 (6 months after rule) 25% of all new handsets must be ALI- capable by July 31, 2002 (6 months after rule)   25% of all new handsets must be ALI- capable by Dec. 31, 2001 (same as rule) 10% of all new handsets must be ALI- capable by Dec. 31, 2002 (1 year after rule, 15% less)
50% of all new handsets activated must be ALI- capable by June 30, 2002 50% of all new handsets activated must be ALI- capable by March 31, 2003 (9 months after rule) No 50% benchmark   40% of all new handsets must be ALI- capable by March 31, 2002; 65% by June 30, 2002 (June requirement exceeds rule by 15%) 50% of all new handsets must be ALI- capable by Dec. 1, 2003 (18 months after rule)
100% of all new handsets must be ALI- capable by Dec. 31, 2002 100% of all new digital handsets must be ALI- capable by Dec. 31, 2003 (1 year after rule) 100% of all new handsets must be ALI- capable by Dec. 31, 2002 (same as rule)   100% of all new digital handsets must be ALI- capable by Sept. 30, 2002 (3 months earlier than rule) 100% of all new handsets must be ALI- capable by Dec. 1, 2004 (2 years after rule)
By Dec. 31, 2005 achieve 95% penetration of ALI- capable handsets 100% of all new consumer handsets must be ALI- capable by Dec. 31, 2005 (1 year after rule) By Dec. 31, 2005 achieve 95% penetration of ALI- capable handsets (same as rule)   By Dec. 31, 2005 achieve 95% penetration of all consumer handsets are E-OTD capable (same as rule) By Dec. 31, 2005 achieve 95% penetration of ALI- capable handsets (same as rule)